Purchase orders
16 POs · every line priced from its contract
Every line shows its pricing mechanic breakdown and CBAM exposure.
Open POs
3
sent / acknowledged / in transit
Delivered YTD
13
closed goods receipts
PO value YTD
€261.1k
2026-01 → now
CBAM exposure YTD
€176.6
After 97.5% free allocation
All purchase orders
Click a row to see the full pricing breakdown.
| PO # | Supplier | Status | Issued | Expected | Lines | Value | CBAM |
|---|---|---|---|---|---|---|---|
| DRAFT-0501 | Ovako Alloy Bars | draft | 18 Apr 2026 | 23 May 2026 | 1 | €11.2k | — |
| PO-2026-0402 | Aperam Stainless France | acknowledged | 14 Apr 2026 | 26 May 2026 | 1 | €18.7k | — |
| PO-2026-0401 | ArcelorMittal Dunkerque | in-transit | 08 Apr 2026 | 06 May 2026 | 1 | €19.4k | — |
| PO-2026-0306 | İçdaş Biga | delivered | 02 Mar 2026 | 18 Mar 2026 | 1 | €14.3k | €45 |
| PO-2026-0301 | ArcelorMittal Dunkerque | delivered | 02 Mar 2026 | 20 Mar 2026 | 1 | €15k | — |
| PO-2026-0208 | İçdaş Biga | delivered | 12 Feb 2026 | 28 Feb 2026 | 1 | €10.8k | €35 |
| PO-2026-0206 | Riva Acciaio | delivered | 10 Feb 2026 | 25 Feb 2026 | 1 | €16.2k | — |
| PO-2026-0205 | Aperam Stainless France | delivered | 08 Feb 2026 | 22 Feb 2026 | 1 | €5.3k | — |
| PO-2026-0201 | thyssenkrupp Steel Europe | delivered | 02 Feb 2026 | 18 Feb 2026 | 2 | €19.1k | — |
| PO-2026-0203 | Ovako Alloy Bars | delivered | 30 Jan 2026 | 14 Feb 2026 | 1 | €6.3k | — |
| PO-2026-0101 | ArcelorMittal Dunkerque | delivered | 28 Jan 2026 | 12 Feb 2026 | 2 | €26k | — |
| PO-2026-0102 | Aperam Stainless France | delivered | 20 Jan 2026 | 05 Feb 2026 | 2 | €28k | — |
| PO-2026-0106 | Riva Acciaio | delivered | 10 Jan 2026 | 25 Jan 2026 | 2 | €29.2k | — |
| PO-2026-0105 | Hyundai Steel | delivered | 10 Jan 2026 | 30 Jan 2026 | 1 | €12.9k | €97 |
| PO-2026-0104 | Ovako Alloy Bars | delivered | 06 Jan 2026 | 22 Jan 2026 | 1 | €9.2k | — |
| PO-2026-0103 | thyssenkrupp Steel Europe | delivered | 02 Jan 2026 | 18 Jan 2026 | 1 | €19.4k | — |